For an enterprise-owned data center, water use can affect operating cost and expansion decisions. A campus adding AI capacity may need to support denser computing while working within existing cooling infrastructure and local water constraints.
Liquid cooling can sound like a commitment to consume more water. But circulating coolant through servers and consuming water to reject heat are different things. A closed coolant loop carries heat away from the equipment. The outdoor cooling system determines whether removing that heat requires evaporation, dry cooling, or a combination.1, 2
Warmer coolant can make dry heat rejection practical for more hours of the year, depending on outdoor conditions and equipment performance. That can reduce reliance on water-assisted cooling. Avoiding mechanical chilling can also save energy, but the water and energy results depend on the complete design.1, 3
Schneider Electric’s white paper of 21 September 2026 illustrates that potential. In modeled 100 MW designs using adiabatic heat rejection, an optimized liquid-cooled AI architecture reduced annual on-site cooling-water use by 48% in Dallas (from about 382,000 to 197,000 cubic meters) and by 53% in Paris (from about 108,000 to 51,000), compared with an air-cooled AI design. These are vendor-modeled results, not measurements from operating enterprise facilities or savings forecasts for your site.4
The lesson is that cooling architecture, operating temperature and climate need to be evaluated together.
A warmer technology-cooling loop is not simply a higher setpoint for an existing chilled-water system. The technology loop supplies coolant to the IT equipment; a coolant distribution unit (CDU) may transfer its heat into a separate facility-water loop. Each side has its own temperature, flow and equipment requirements. ASHRAE recognizes a W45 liquid-cooling class with an upper temperature limit of 45°C (113°F), but the selected hardware’s approved conditions still govern the design.2, 5
Before choosing an architecture, bring IT and facilities together around five decisions:
- Equipment requirements: what coolant temperatures, flow rates, fluid quality and warranty conditions does the selected platform require?
- Heat rejection: can the existing plant support the load, including remaining air-cooled equipment, or will dry, adiabatic or evaporative equipment need to be added?
- Local conditions: how do summer design temperatures, seasonal weather, water availability and utility charges affect the options?
- Reliability and operations: what happens during a cooling failure or maintenance event, and how will controls, leaks, coolant quality and recovery be managed?
- Whole-project economics: what are the capital cost, annual water and energy use, maintenance needs and expansion implications of each workable design?2, 3
For an existing facility, a dedicated AI zone may provide a practical way to introduce a different cooling architecture while retaining air cooling elsewhere. Its water benefit will depend on how heat leaves the site.2
A liquid-cooled expansion can offer a chance to improve water performance while meeting the business’s computing needs. Evaluating the hardware, temperature range and heat-rejection options together gives your team a clearer view of the costs, savings and reliability it can reasonably expect.
Sources
Checked 30 September 2026. Water figures are on-site cooling water only; they do not include water used to generate the site's electricity.
- Vendor source. Schneider Electric · White Paper 220, Water usage at AI scale: insights from a 100 MW comparative analysis, 21 September 2026 (summary page)
- Vendor source. Vertiv · Liquid and immersion cooling options for data centers
- Research source. ASHRAE · AI data center framework: energy and thermal efficiency
- Vendor source. Schneider Electric · Climate Week NYC 2026 press release, section "Supporting responsible AI infrastructure growth"
- Research source. ASHRAE · AI data center framework: introduction and purpose (liquid-cooling classes W17 to W+)