DataCenterUpdate Enterprise data center market intelligence

Power

Grid supply and electricity cost for facilities already running: what changed, what the figure measures, and the question it raises for your site.

What changed this week

Nothing new yet this week (12–18 October 2026). Latest changes, 21–27 September 2026:

Electricity cost · updated monthly

Power prices by state

Latest data: July 2026 · Compared with: July 2025 · Released: 24 September 2026 · Status: preliminary

United States · July 2026 compared with July 2025 · preliminary

  • Commercial +3.4% 14.53¢ per kWh, from 14.05¢
  • Industrial +4.7% 9.77¢ per kWh, from 9.33¢
  • Year to date (January–July): commercial +5.6%, industrial +5.9%

These are national averages for all commercial or all industrial customers. They are not any facility's rate or bill: compare your own rate class and supply contract.

Largest measured movements, July 2026 compared with July 2025

Percentage change in each state's average price for the sector. Ranked by the size of the change, not by price. EIA's figures do not say why prices moved, and DCU does not attribute a cause.

Commercial

Largest increases

  1. +24.4%
  2. +22.3%
  3. +15.7%
  4. +15.4%
  5. +14.4%

Largest decreases

  1. −13.1%
  2. −5.5%
  3. −5.3%
  4. −4.5%
  5. −4.3%

Industrial

Largest increases

  1. +59.1%
  2. +29.8%
  3. +27.9%
  4. +21.4%
  5. +21.0%

Largest decreases

  1. −27.5%
  2. −12.0%
  3. −11.3%
  4. −7.7%
  5. −7.0%
All 50 states and DC
Cents per kWh, July 2026 Commercialvs 2025 Industrialvs 2025
Alabama 14.83¢+1.6% 8.42¢+3.7%
Alaska 23.29¢+1.3% 24.81¢+27.9%
Arizona 13.12¢−2.2% 9.35¢+0.9%
Arkansas 11.76¢+10.8% 7.84¢+8.3%
California 30.56¢+1.6% 25.11¢−0.6%
Colorado 13.81¢+4.2% 9.54¢+0.1%
Connecticut 19.87¢−13.1% 17.29¢−7.0%
Delaware 13.80¢+10.0% 11.71¢+5.6%
District of Columbia 23.88¢+15.4% 32.15¢+59.1%
Florida 11.37¢+0.6% 9.17¢+2.9%
Georgia 12.54¢+0.4% 10.03¢−7.7%
Hawaii 43.63¢+24.4% 39.33¢+29.8%
Idaho 10.16¢+5.9% 9.02¢+9.5%
Illinois 15.19¢+11.2% 11.87¢+11.6%
Indiana 13.30¢−5.5% 9.16¢−0.5%
Iowa 13.27¢+0.7% 9.99¢+10.1%
Kansas 12.04¢+3.1% 8.52¢+5.6%
Kentucky 11.95¢+2.7% 7.51¢+2.7%
Louisiana 10.97¢−5.3% 6.08¢−12.0%
Maine 21.64¢+2.7% 13.94¢−11.3%
Maryland 17.51¢+15.7% 16.21¢+18.7%
Massachusetts 24.41¢+4.9% 20.25¢+1.6%
Michigan 16.46¢+10.0% 9.81¢+9.7%
Minnesota 13.49¢+2.4% 10.34¢+5.8%
Mississippi 13.65¢+7.2% 7.66¢+0.7%
Missouri 12.64¢+3.5% 9.87¢+4.3%
Montana 13.33¢+3.9% 7.71¢0.0%
Nebraska 9.39¢−1.9% 10.00¢+11.1%
Nevada 9.72¢−4.1% 10.04¢+2.1%
New Hampshire 20.63¢+4.5% 18.17¢+8.5%
New Jersey 19.17¢+4.4% 15.63¢+4.8%
New Mexico 11.90¢−4.5% 4.16¢−27.5%
New York 24.18¢+4.9% 10.81¢+7.5%
North Carolina 10.73¢+10.1% 8.37¢+7.7%
North Dakota 8.22¢+5.5% 8.21¢+7.7%
Ohio 14.06¢+22.3% 10.95¢+21.0%
Oklahoma 10.32¢+4.0% 8.16¢+21.4%
Oregon 10.60¢+0.1% 8.92¢+3.8%
Pennsylvania 13.86¢+9.7% 11.04¢+11.9%
Rhode Island 23.43¢+5.4% 22.86¢+7.3%
South Carolina 11.61¢+5.8% 7.84¢−0.5%
South Dakota 12.17¢+3.8% 9.83¢+5.4%
Tennessee 13.43¢+4.8% 7.13¢−1.5%
Texas 8.47¢−4.3% 7.07¢+7.0%
Utah 10.85¢+3.9% 9.10¢−3.2%
Vermont 20.71¢+6.8% 13.07¢+6.9%
Virginia 11.68¢+14.4% 10.07¢+3.8%
Washington 11.78¢+4.8% 7.51¢+4.2%
West Virginia 11.44¢+2.2% 8.40¢+5.3%
Wisconsin 13.93¢+4.2% 10.46¢+6.1%
Wyoming 10.26¢+1.0% 8.62¢−3.5%
U.S. average 14.53¢+3.4% 9.77¢+4.7%

Government source. U.S. Energy Information Administration, Electric Power Monthly, Table 5.6.A (latest month) and Table 5.6.B (year to date), data for July 2026, released 24 September 2026. Preliminary estimates, revised in later editions. Ranks are among 51 jurisdictions: the 50 states and DC.

Grid supply · PJM region, including Virginia and Ohio

The PJM grid secured less capacity than its reliability requirement for 2028/29

Delivery year: 2028/29 · Auction results: 14 July 2026 · Second auction in a row below requirement

  • 6,831 MWbelow PJM's reliability requirement (unforced capacity). Previous auction: 6,516 MW.
  • 14.7%estimated total reserve margin, against a 20% target
  • $325.00per MW-day: the 2028/29 wholesale auction clearing price, at the cap. A market result, not a facility bill.

PJM runs this auction to secure enough generation, and demand that can be reduced, for a future year. For 2028/29 it secured 149,182 MW of unforced capacity, a rating that discounts each resource for how reliably it can deliver. That was 6,831 MW short of the 156,013 MW requirement. PJM says the shortfall "does not necessarily mean that the PJM system will be unable to serve load reliably", but that it "would have to operate with slimmer reserves and greater level of risk."

Two reserve margins appear in the report. 14.7% is PJM's estimate for the whole region, counting capacity bought in the auction and capacity that some utilities commit from their own resources. 14.4% counts the auction alone. Both are below the 20% target, which PJM sets to hold the expected loss of load to one day in ten years.

This is the second auction in a row to clear more than one percentage point below that target. PJM's report says its current tariff provides for a separate Reliability Backstop Auction if three consecutive auctions do so. The report describes changes to those backstop rules as work in PJM's stakeholder process, not as approved rules.

Wholesale auction clearing price, $ per MW-day

2024/252025/262026/272027/282028/29
$28.92$269.92$329.17$333.44$325.00
Delivery year$ per MW-day
2024/25$28.92
2025/26$269.92
2026/27$329.17
2027/28$333.44
2028/29$325.00

Region-wide wholesale clearing prices for each delivery year, as listed in PJM's 2028/29 report. The 2027/28 and 2028/29 auctions both cleared at their price caps. These are market results, not facility bills: PJM notes that its auction totals do not equal the cost to customers, because load whose supply is hedged is not exposed to the clearing price.

The question for an existing facility in PJM:
What is our peak load contribution, how is it calculated in our utility zone, and how do capacity charges reach our bill under our supply arrangement?

PJM's capacity manual separates two things. Your local utility assigns each customer a peak load contribution: a share of the zone's weather-normalized peak from the previous summer, set before each delivery year. The capacity obligation belongs to whoever serves your load, your utility or your supplier: it is the sum of its customers' peak load contributions, scaled by zonal and PJM-wide factors. Neither is the same as your facility's rated MW.

How peak load contributions are calculated varies by utility zone. How capacity charges reach your bill depends on how you buy power: default service from your utility, a contract with a competitive supplier (with capacity cost passed through, fixed, or bundled into the price), or a utility that supplies its own capacity. Your utility or supplier can tell you which applies.

Correction, 24 September 2026. We removed a per-MW-year figure calculated from the auction clearing price, which could be read as a facility cost, and rewrote the facility question to separate a customer's peak load contribution from its supplier's capacity obligation. We also described PJM's backstop rule changes as proposals.

Grid operator source. PJM Interconnection, 2028/2029 Base Residual Auction Report (PDF), 14 July 2026, pages 3–5; and PJM Manual 18: PJM Capacity Market (PDF), Revision 62, effective 17 December 2025, sections 7.4–7.5.