Standards & Guidance

A new edition doesn't automatically change the rules for your facility. Here's what's being revised, and what to confirm before buying equipment, renovating or expanding.

Whether an edition applies to your project depends on what your state, local authority, insurer or contract adopts. We report the status at the standards body and say what to confirm.

We follow 8 standards bodies for changes that could affect your data center: NFPA · IEEE · ASHRAE · UL · ICC · TIA · BICSI · Uptime Institute

NFPA Open for comment

Could emissions controls shut down your emergency generator? NFPA is considering a change

For Level 1 emergency power · Comments close 14 October 2026

NFPA 110, Standard for Emergency and Standby Power Systems (2025 edition), proposed TIA No. 1950

Could affect
Choosing and configuring backup generators where emergency power is classified Level 1, particularly Tier 4 certified engines with SCR emissions controls.
What to check
Whether any of your emergency power is classified Level 1; whether your Tier 4 engines with SCR can derate or shut down when the emissions system demands it, and how that is managed; which NFPA 110 edition your authority having jurisdiction enforces.

The proposed amendment adds a paragraph to NFPA 110: “Where used for permanent Level 1 applications, EPA-mandated inducement engine shutdowns due to emissions system controls that are required on Tier 4 certified engines with SCR shall be prohibited.” It extends to the 2025 edition an amendment already made to the 2022 edition; identical language has been accepted for the 2028 edition. It was submitted by Cummins.

NFPA 110 reserves Level 1 for the most critical systems, where a failure could put lives at risk. Many data center backup systems are classified differently, so this matters most where a facility’s generators also serve life-safety loads, or where a hospital, 911 center or similar operation shares the plant.

A related question in Virginia. Virginia now requires data center generator permits to meet Tier 4-equivalent emission limits, and its definition of “Tier 4 equivalent” includes selective catalytic reduction (SCR) “or equivalent.” That is an emissions requirement, not a Level 1 rule, and it does not by itself mean a site’s engines are Tier 4 certified or subject to inducement shutdowns. Where both apply, owners should ask their generator supplier how emissions-control faults are handled on emergency loads.

Source: NFPA 110 proposed TIA No. 1950 (PDF) · last verified 12 October 2026

NFPA Open for comment

Fire protection rules for IT rooms are being revised: the NFPA 75 draft is open for comment until 6 January

Comments close 6 January 2027

NFPA 75, Standard for the Fire Protection of Information Technology Equipment (next edition, Fall 2027 cycle)

Could affect
Fire protection design for computer rooms and IT equipment areas: renovations, new rooms, and changes to suppression or detection.
What to check
Which NFPA 75 edition your fire marshal and insurer apply (the current edition is 2024); whether planned IT room work would be affected by the proposed changes in the First Draft Report.

NFPA 75 covers protecting IT equipment and IT equipment areas from fire and its effects: smoke, corrosion, heat and water. The current edition is 2024. For the next edition, NFPA posted the First Draft Report on 18 September 2026; public comments on it close on 6 January 2027.

We have not yet reviewed the draft’s specific changes. This entry will be updated when we have.

Standards process: the Second Draft is due 6 October 2027.

Source: NFPA 75 document information page · last verified 8 October 2026

NFPA Current edition

Adding batteries? Check which fire-safety requirements apply

NFPA 855, Standard for the Installation of Stationary Energy Storage Systems (2026 edition)

Could affect
Installing or expanding battery energy storage, which can include some lithium-ion UPS installations, depending on capacity, chemistry and use.
What to check
Whether your planned battery installation falls within NFPA 855’s scope, which edition your authority having jurisdiction enforces, and errata 855-26-1 (Table 9.7.6).

NFPA 855 provides “the minimum requirements for mitigating the hazards associated with” energy storage systems. The current edition is 2026; an erratum (855-26-1, Table 9.7.6) was issued on 13 October 2025.

Whether a given UPS battery system is within the standard’s scope depends on its details; confirm with your authority having jurisdiction rather than assuming either way.

Standards process: work on the 2029 edition (Annual 2028 revision cycle) is under way; the First Draft Report is due 24 March 2027.

Source: NFPA 855 document information page · last verified 12 October 2026

NFPA Current edition

The 2026 National Electrical Code is out, but your state may still enforce an earlier edition

NFPA 70, National Electrical Code (2026 edition)

Could affect
Electrical design, permitting and inspection of new or expanded IT space and its power systems.
What to check
Which NEC edition your state and local jurisdiction enforce today, and whether adoption of the 2026 edition is scheduled before your project is permitted.

The current edition of the NEC is 2026. NFPA describes the code as “enforced in all 50 states,” but each state and many localities adopt editions on their own schedule, so the edition that applies to a project can be older.

Standards process: NFPA is reorganizing the code over several editions, with completion targeted for 2029; the 2029 First Draft Report is due 10 June 2027.

Source: NFPA 70 document information page · last verified 8 October 2026

ASHRAE Current edition

Planning an expansion? Check which edition of the data center energy standard your code uses

ANSI/ASHRAE Standard 90.4, Energy Standard for Data Centers (2025 edition)

Could affect
Energy compliance for a new or expanded data center where the local energy code references Standard 90.4.
What to check
Whether your jurisdiction’s energy code references 90.4 and which edition; ask your design engineer what the 2025 changes mean for your electrical and cooling design.

A 2025 edition of ASHRAE Standard 90.4, the energy standard written for data centers, is current. It is intended for adoption into energy codes, and it relies on Standard 90.1 for the building envelope, service water heating and lighting. Which edition applies to your project depends on the energy code your jurisdiction has adopted, so the same expansion can face different requirements in different places.

No public review of 90.4 was open on ASHRAE’s public review page when we checked.

Source: ASHRAE Standard 90.4 page · last verified 8 October 2026